Update z meho developerskeho projektu na sklady

Dlouho jsem nepsal jak pokracuje muj developersky projekt se stavenim skladu. Takto vypadal nedavny update od architekta. 1. Architectural 85% complete 2. Structural plans 90% complete 3. MPE plans will be completed in less than 2 weeks 4. Grading plans – Complete 5. Parcel map – tentative. Awaiting final details from Civil Engineer. It should be done next week 6. Submittal … Continue reading Update z meho developerskeho projektu na sklady Zobrazit více